2026-08-16 · Air Force flight academy, Wuchang, Heilongjiang
4 套天然气供应设备护航空军某飞行学院冬季供暖Four gas supply systems for an Air Force flight academy
2 套 1000 Nm³/h LNG 气化站 + 2 套 1000 Nm³/h CNG 减压站,2025 年 4 月签约、12 月完成验收,跨冬季交付。2×1000 Nm³/h LNG stations plus 2×1000 Nm³/h CNG stations; signed April 2025, accepted December 2025.

01 / Scope
供货与实施范围Scope of supply
- LNG 气化站成套(储罐、卸车增压、空温+水浴气化、调压计量)LNG station package
- CNG 减压站成套(两级减压、换热、计量)CNG reducing station package
- 现场安装、氮气置换、升压调试与培训Installation, purging, commissioning, training
- 冬季运行工况复核与保供值守方案Winter duty review and supply assurance plan
02 / Data
项目参数Project data
| LNG 气化站LNG stations | 2 × 1000 Nm³/h2 × 1000 Nm³/h |
|---|---|
| CNG 减压站CNG stations | 2 × 1000 Nm³/h2 × 1000 Nm³/h |
| 签约 / 验收Signed / accepted | 2025-04-22 / 2025-12-242025-04-22 / 2025-12-24 |
| 站址Site | 黑龙江五常拉林镇Lalin, Wuchang, Heilongjiang |
| 核心约束Constraint | 冬季极端低温下的气化能力Vaporisation capacity at extreme low temperature |
03 / Timeline
实施节点Milestones
2025-04
签约,确认 4 套设备配置与站址条件Contract signed, configuration and site confirmed
2025-08
工艺流程图与平面布置确认,进入制造P&ID and layout frozen, fabrication starts
2025-11
设备到场,完成安装与氮气置换Delivery, installation and nitrogen purge
2025-12
升压调试、联动试运行,12-24 完成验收Commissioning and acceptance on 24 December